LÜ Yuanqiang, ZHANG Xingqin, JIANG Haibo, YANG Lingyun. Optimal slope rate of loess slope formed by construction excavation in west Shanxi[J]. COAL GEOLOGY & EXPLORATION, 2011, 39(6): 58-62. DOI: 10.3969/j.issn.1001-1986.2011.06.014
Citation: LÜ Yuanqiang, ZHANG Xingqin, JIANG Haibo, YANG Lingyun. Optimal slope rate of loess slope formed by construction excavation in west Shanxi[J]. COAL GEOLOGY & EXPLORATION, 2011, 39(6): 58-62. DOI: 10.3969/j.issn.1001-1986.2011.06.014

Optimal slope rate of loess slope formed by construction excavation in west Shanxi

  • The paper, combined with engineering practices in loess area of west Shanxi, through field investigation and measurement, laboratory experiments, numeric calculation, aimed at different slope height (8m, 16m, 24m, 32m, 45m), using analogy, anti-algorithm, literature and numeric calculation to carry out analysis and study, derived the optimal rate of loess slope with different height.The results have been used in construction projects of the area.It can save project investment, protect the geological environments in construction area, also provide reference for similar construction projects in other areas.
  • loading

Catalog

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return